A vSAN administrator has a group of requirements from the application team, which mandates spreading the components across storage devices as much as possible.
What should the vSAN Administrator consider to achieve such a requirement for building a new vSAN cluster? (Choose two.)
Configure disk striping in OSA
Configure disk striping in ESA
Enable Force Provisioning in OSA
Enable deduplication for vSAN
Create a dedicated Storage Pool in ESA
Correct answer: AD
Question 2
A site administrator wishes to implement HCI mesh between two clusters on vSAN that are located in geographically separate sites and which are administered within a single datacenter.
Which two requirements should the vSAN administrator consider to accomplish this goal? (Choose two.)
Either Layer 2 or Layer 3 communications can be used
A leaf spine topology is required for core redundancy and reduced latency
NIC teaming must be implemented for the vSAN network vmkernel port
The configuration must meet the same latency and bandwidth requirement as local vSAN
Encryption must be disabled prior to configuring HCI mesh
Correct answer: AD
Question 3
An administrator has 24 physical servers that need to be configured with vSAN. The administrator needs to ensure that a single rack failure is not going to affect the data availability. The number of racks used should be minimized.
What has to be done and configured to achieve this goal?
Distribute servers across at least two different racks and configure two fault domains
Configure disk groups with a minimum of four capacity disks in each server and distribute them across four racks
Enable deduplication and compression
Distribute servers across at least three different racks and configure three fault domains Most Voted