What is the definition of done good for? Choose all that apply.
This way documentation is obligated and cannot be skipped
It creates a shared understanding of what done means
Management knows what the work of the developer needs to be checked for
It helps the developers know how much work to select during the sprint planning
Correct answer: BD
Explanation:
The DoD helps the developers know how much work needs to be done, and therefore they can decide what should be part of the sprint. It also creates a shared understanding of what done means. This is likely to include documentation, but that depends on the decisions of the organization and team. Scrum does not dictate this.
The DoD helps the developers know how much work needs to be done, and therefore they can decide what should be part of the sprint. It also creates a shared understanding of what done means. This is likely to include documentation, but that depends on the decisions of the organization and team. Scrum does not dictate this.
Question 2
How much time will there be after a sprint before the next one starts?
Enough to deploy the increment and update the product backlog based on the outcome of the sprint review
Enough to clean up lingering definition of done points
None, a new sprint starts immediately after the end of the previous one
At most a week for a one-month sprint
Correct answer: C
Explanation:
The scrum guide says: 'A new Sprint starts immediately after the conclusion of the previous Sprint.'
The scrum guide says: 'A new Sprint starts immediately after the conclusion of the previous Sprint.'
Question 3
What do scrum artifacts represent?
Work that needs to be done
Flow and feedback
Work or value
Visual representation of the progress
Correct answer: C
Explanation:
The scrum artifacts are: product backlog, sprint backlog and the increment. They represent work or value.
The scrum artifacts are: product backlog, sprint backlog and the increment. They represent work or value.