The availability check (ATP) is carried out based on which of the following dates?
The material availability date
The transportation planning date
The goods issue date
The loading date
Correct answer: A
Question 2
In the system, it is possible to have zero stock available and still receive a confirmed schedule line in the sales order. Which of the following states the reason for this confirmation?
Stock will be taken from another delivery at the shipping point.
The system automatically searches other plants for inventory and transfers this inventory to the plant with zero inventory in the sales order.
The availability check that was carried out included a replenishment lead time in the scope of check.
A stock transfer will be created by inventory management when you save the sales order.
Correct answer: C
Question 3
During sales order processing, a user will be alerted when stock is not available for material entered in the sales order if the availability check was carried out.
In which of the following ways will the user be alerted about this situation?
An error message will appear on the status bar alerting the user to the situation.
The schedule line will be marked and highlighted by the system.
The availability control screen will be displayed.
The incompletion log will display the unconfirmed schedule line as a missing field.