You want to use the function "Read PP master data" in the production order.
However, while calling the function you receive an error message.
What could be the reason?
The material availability check has been performed.
Goods movements have been posted.
The production order has been released.
Order papers have been printed.
Correct answer: B
Question 2
Which objects can affect the calculation of capacity requirements for an operation? (Choose three)
Standard values (routing)
In-house production time (material master)
Transport time (routing)
Formulas (work center)
Operation control key (routing)
Correct answer: ADE
Question 3
In the Customizing for requirements planning, a project team notices that the alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP type PD. The number in each of these alternatives represents a firming type.
What does a firming type define? (Choose two)
Handling existing procurement proposals outside the planning time fence.
Handling existing procurement proposals within a planning time fence.
Handling new requirements within the planning time fence.
Handling new procurement proposals that need to be created due to new requirements within the planning time fence.