Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?
Historical relationships
Dependency determination
Bottom-up estimating
Rolling wave planning
Correct answer: D
Question 2
An output of the Create WBS process is:
Scope baseline.
Change requests.
Accepted deliverables.
Variance analysis.
Correct answer: A
Question 3
A tool or technique used in the Control Procurements process is: