The Project Manager is involved in acquiring the project team on a highway expansion project. She is presently discussing salary, working hours, travel, and benefits. What is the key tool she is utilizing?
Staffing management plan
Organizational chart
Project team directory
Negotiations
Correct answer: D
Question 2
As the buyer is involved in creating request for proposals (RFP). for an infrastructure project, they will provide these to sellers of services. All of the following are names used for a seller except?
Contractor
Service provider
Supplier
Acquiring organization
Correct answer: D
Question 3
What type of contract provides the buyer with the most risk and seller the least risk?