Your client is involved in automation control systems installation. Over the years, they have analyzed their total project spend on specific resource classes. They have identified that their cost spread distribution factor on a 10 spread point scale resembles: 0-4-10-11-14-13-10-4-0-0.
Identify two ways to handle this kind of a spread on their budgets and forecasts. (Choose two.)
Create a new spread curve or edit an existing spread curve to exactly match the spread points and attach to a project template.
Create a new spread curve or edit an existing spread curve to exactly match the spread points and attach to the resource class.
Use the predefined Bell Curve spread with small deviations on the spread points.
Use the predefined S-Curve spread with small deviations on the spread points.
Correct answer: BC
Question 2
While opening an organization tree on the Manage Organization Trees page, you notice that the hierarchy status is displayed as Inactive.
Identify the two reasons for the organization tree to be in Inactive status. (Choose two.)
You used Create Tree in the action menu.
You used Create Tree Version in the action menu.
You used View Tree Version in the action menu.
You selected the Edit icon for opening the hierarchy.
You opened the hierarchy by clicking the name.
Correct answer: AD
Question 3
In your customer site, the capitalized interest calculation is implemented on their project types. Which option represents the costs considered in the interest calculation? (Choose the best answer.)
common costs on the project/task
expenditure type exclusions on the Capitalized Interest rate name
expenditure type exclusions on the Capitalized Interest rate schedules
expenditure items whose cost spreads across multiple assets that are capitalized
expenditure items whose costs are applied to a single asset or multiple assets