Question 1
Your customer has implemented Oracle Project Portfolio Management Cloud recently and they have hired new employees for their Professions Services business. These employees are set up in Oracle Human Capital Management Cloud, but the Project Administrators are unable to add them as resources in the Planning Resource Breakdown Structure. 
What are three conditions for new employees to show up in the list?
  1. All new employees created as persons must have an active project role.
  2. All new employees created as persons must have an active supervisor.
  3. All new employees created as persons must have an active assignment.
  4. All new employees created as persons must be assigned to a department.
  5. Current date is before the effective date of the resource, and you did not enable the “Include people with future-dated effective start dates” option during the search.
Correct answer: ACE
Question 2
You configure one OTBI using Project Cross Subject Area Analysis Real Time. You notice that all measures (Budget, Forecast, Cost, Commitments, Revenue, and Invoice) are not available for Bill-To-Customer and Contract and Contract Line dimensions. Identify the reason for this behavior.
  1. The Bill-To-Customer dimension applies to Invoice measures, and the Contract and Contract Line dimensions apply to Revenue and Invoice measures.
  2. The Bill-To-Customer dimension does not apply to Invoice measures, but the Contract and Contract Line dimensions apply only to Revenue and Invoice measures.
  3. The Bill-To-Customer dimension applies only to Invoice measures, but the Contract and Contract Line dimensions do not apply to Revenue and Invoice measures.
  4. The Contract and Contract Line dimensions apply only to Invoice measures.
  5. The Bill-To-Customer dimension applies only to Revenue and Invoice measures.
Correct answer: E
Question 3
You recently made some changes to a project contract and the current status of the contract is Under Amendment. Identify the correct sequence of activities that can take place on that contract.
  1. On Hold > Pending Approval > Active
  2. On Hold > Pending Acceptance > Active
  3. Pending Approval > Pending Acceptance > Active
  4. Pending Acceptance > Pending Approval > Active
Correct answer: C
Explanation:
Reference: https://docs.oracle.com/cloud/latest/common/FASCC/FASCC1124283.htm
Reference: https://docs.oracle.com/cloud/latest/common/FASCC/FASCC1124283.htm
EXAM SIMULATOR

How to Open TQB Files?

Use Taurus Exam Simulator to open TQB files

Taurus Exam Simulator


Taurus Exam Simulator for Windows/macOS/Linus

Download

Taurus Exam Studio
Enjoy a 20% discount on Taurus Exam Studio!

You now have the chance to acquire Exam Studio at a discounted rate of 20%.

Get Now!
-->