You are the production supervisor at a chemical processing plant. You must track attributes for each batch of chemicals. Automated quality orders must be generated when a batch order for these chemicals is reported as finished.
You need to ensure that the values of attributes are updated and tracked.
What three actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
Assign the attributes to the chemicals
Assign the attributes to the appropriate test on the test group
Create attribute types
Set up batch attributes
Create a test instrument for each attribute
Correct answer: ADE
Question 2
A manufacturer produces HDMI cables. Typically, the item is manufactured.
The manufacturer will occasionally buy unbranded HDMI cables from a vendor in order to keep up with demand. The company must use the same item number whether they make or buy the item.
What should you do?
Select route type as vendor on the route operation when the item is to be purchased.
In default order settings, select Production for the default order type
Create a new vendor resource when the item is to be purchased
In default order settings, select Purchase for the default order type
Correct answer: A
Question 3
A company produces paints and assembles bicycle frames.
You must account for paint drying time before assembly operations can begin. You need to set up the operation to encompass queue times.
Which two options can you use? Each correct answer presents part of solution.
NOTE: Each correct selection is worth one point.
Enter a value in the queue time after field for the painting operation
Make a resource group for each size and color and assign that group to the operation
Enter a value in the transit time on the painting operation
Enter a value in the queue time before field for the assembly operation
Build capabilities for each resource related to color