Where can a project manager find risk-rating rules?
Risk probability and impact matrix
Organizational process assets
Enterprise environmental factors
Risk management plan
Correct answer: B
Question 2
There are five inputs to the quantitative risk analysis process. Which one of the following is NOT an input to the perform quantitative risk analysis process?
Risk register
Cost management plan
Risk management plan
Enterprise environmental factors
Correct answer: D
Question 3
Your project has several risks that may cause serious financial impact should they happen. You have studied the risk events and made some potential risk responses for the risk events but management wants you to do more. They'd like for you to create some type of a chart that identified the risk probability and impact with a financial amount for each risk event. What is the likely outcome of creating this type of chart?