A company's new approach to selling requires extensive resource planning. A team of process analysts has been assembled to perform this work. Which option is
sufficient to enforce consistent simulations behavior across the team? All analysts:
set the same random number seed and process availability start and end dates in the simulation profiles.
set the same random number seed, process availability start and end dates, and maximum simulation duration in the simulation profiles.
set unique random number seed, process availability start and end dates, maximum simulation duration and maximum number of process invocations in the simulation profiles.
set unique random number seeds and process availability start and end dates in the simulation profiles.
Correct answer: A
Question 2
When reviewing the simulations results, the process analyst discovered that for each task in the process that has multiple output criteria, the simulation engine would make a random selection of an output path, and generate outgoing tokens for each output defined in the output criterion. Which of the following settings was used during the simulation?
Randomly to a single path.
Based on an expression.
Based on probabilities to a single path.
Based on probabilities to multiple paths.
Correct answer: C
Explanation:
Question 3
During an exception period, a resource could not complete a task before the end of the task's processing time. What should be done to ensure that the resource remains allocated until the task is completed?
Check "Use resources time required as a task processing time".
Check the preference "Run simulation without resource requirements".
Increase the "Task duration" to match the resource required time.
Set the task's "Resource wait time" to be the resource shortage time.