A customer needs a Synergy Proof of Concept (PoC) using Image Streamer.
What is the minimum number of Synergy frames needed for this PoC?
1
2
3
5
Correct answer: C
Question 2
A customer has a ProLiant DL based Gen10 server solution hosting an I/O intensive 2TB database. The customer needs to dramatically increase the performance of their existing system.
Which solution will provide the maximum performance possible for their application?
Install HPE Scalable Persistent Memory
Move the OS to an M.2 SSD drive
Upgrade the current processor to a Xeon-Platinum
Install DD4 Smart Memory
Correct answer: A
Question 3
A customer received their three frame Synergy system. However, they are missing a link cable that connects the frame link module between the frames.