Your team uses Story Points to estimate User stories.
Halfway through a Sprint, you are not seeing the progress you expected. The Team feels some Stories are not estimated correctly, when compared to other Stories.
How should you address this?
Complete incomplete Stories
Increase or re-estimate Velocity
Re-estimate all small Stories
Switch to using Ideal days
Correct answer: A
Question 2
Why is a Product Owner not allowed to define the workload of the Development Team for a new Sprint?
This conflicts with the principle of Self-Management of the Development Team.
The Product Owner does not know the velocity of the Development Team.
The Scrum Master is responsible for the velocity of the Development Team.
The Scrum Master and the Product Owner must agree on the workload of the Development Team.
Correct answer: A
Question 3
What is one of the most difficult challenges you face when transitioning your software development team to Scrum?