During a Sprint, the team completes four stories with story points 3, 5, 8 and 2 respectively. They further complete half a story with a story point of 13.
What is the velocity of the team?
18
24.5
31
Correct answer: A
Question 2
Which statement describes Release Planning?
After looking at all the stories in the backlog, the team estimates their effort in detail.
The team meets with the customer to negotiate the scope, cost and time of the release.
The team and the Product Owner agree on an initial plan for the delivery of features.
Correct answer: C
Question 3
Agile planning happens at multiple levels including a daily plan,a sprint plan and a strategic plan.
What term best describes the multi-level planning?