Which of the following activities should be performed during the selection and implementation of a testing tool?
a) Determine whether the organization existing test process needs to change.
b) Conduct a proof of concept.
c) Implement the selected tool on a project behind schedule to save time.
d) Identify coaching and mentoring requirements for the use of the selected tool
a, b and c.
b, c and d.
a, c and d.
a, b and d.
Correct answer: D
Question 2
Which one of the following is true of software development models?
There are always four test levels in the V-model.
In a Rapid Application Development (RAD) project, there are four test levels for each iteration.
In Agile development models, the number of test levels for an iteration can vary depending on the project.
There must be at least four test levels for any software development model.
Correct answer: C
Question 3
Four testers have each submitted an incident report in which each reported a problem with the User log-on process. User log-on is a critical component of the system. The table below describes the four defect reports submitted.
Which Tester has reported the incident MOST effectively, considering the information and priority they have supplied?